Temporary works: the register, the check category and the permit to load

Falsework, formwork, propping, trench support, scaffolding loaded by something other than people. The works nobody is paid for, which fail more often than the permanent works they exist to build.

BS 5975 procedural control · United Kingdom

Temporary works are everything erected to enable the permanent works and then taken away. They carry load, they are frequently designed in a hurry, and because they are not the deliverable they attract less scrutiny than anything else on site. BS 5975 exists to put procedural control around that.

The roles

RoleWhat it is for
Designated Individual Appointed at organisation level. Owns the procedure itself and appoints the coordinators.
Temporary Works Coordinator (TWC) Appointed per project. Maintains the register, sees that each item is designed and checked to the right category, and issues the permits to load and to strike.
Temporary Works Supervisor (TWS) Appointed where the TWC needs eyes on a particular item. Supervises erection against the design and reports back — the TWS does not take the coordinator’s decisions.

The design check categories

Every temporary works design gets a check, and the category decides how independent the checker has to be. It is not a measure of how much checking is done; it is a measure of distance from the designer.

CategoryTypicallyChecked by
0Standard solutions and restricted, simple casesAnother member of the design team
1Simple designs Somebody not involved in the design, within the same organisation
2More complex or unusual designs Somebody from a different team, not involved in the design
3Complex or innovative designs, or those with unfamiliar load pathsAn independent organisation

Categories differ slightly between editions and between company procedures, so a register should record the category that was actually assigned and who assigned it, rather than a number with no author.

The permit to load is not a date

The failure this is all built to prevent is simple to describe: something is erected, somebody is keen to keep the job moving, and load goes on before the erection has been inspected against the design. The paperwork catches up afterwards and records a permit that was issued before anybody looked.

A permit to load should follow an inspection of what was actually built. A permit that follows a date on a programme authorises whatever happens to be standing there.

The same applies to striking. A permit to strike should follow evidence that the striking condition was met — cube results, a concrete maturity figure, a named person’s sign-off — not the passage of a number of days.

“Not in accordance with the design” is a finding, not a failure An inspection that records props at the wrong centres has done its job. What matters is whether load went on afterwards. A register that cannot tell the difference between an item inspected and found wanting, and an item nobody inspected, is not much of a register.

What a register should hold

How Veystrum handles it

Veystrum holds this as a register rather than a folder of documents, and the rules are enforced by the database rather than by convention. A permit to load cannot be recorded against an item with no erection inspection behind it. An item carrying load on a design that was never checked appears on the exception report, with the date the load went on. Withdrawing a permit does not unsay the load — the register keeps both facts, because an investigation two years later asks what was true on a day that has already happened.

This is a summary, not legal advice The authoritative texts are BS 5975 and, for design duties, the Construction (Design and Management) Regulations 2015. Company procedures vary; follow yours.