When Is a Project Notifiable Under CDM 2015?

A construction project must be notified to HSE on form F10 when the work is expected to last longer than 30 working days and have more than 20 workers working at the same time at any point, or to exceed 500 person-days. Either test on its own is enough. The client has the duty to notify, as soon as practicable before the construction phase begins, though someone else may submit it on their behalf.

Sources: CDM 2015 regulation 6 (SI 2015/51, legislation.gov.uk) · HSE: F10 notification of construction project · HSE CDM 2015 FAQ · Last reviewed 27 September 2026

Check your project

Enter what you expect for the whole construction phase. Leave a box blank if you do not know it yet: the checker will say what it cannot decide rather than guess. Nothing you type leaves this page.

The two tests

TestNotifiable when the work is scheduled to
Duration and headcountlast longer than 30 working days and have more than 20 workers working simultaneously at any point
Volume of workexceed 500 person days

The first test needs both halves. A long job with a small crew never meets it, and nor does a short job with a big one, however many people turn up. That is what the second test is for: a long job with a small crew can still pass 500 person-days. A working day is any day on which construction work takes place (regulation 2).

Worked examples

ProjectWorking daysPeak workersPerson-daysNotifiable?
Office refit2530400No: not over 30 days, not over 500 person-days
Warehouse extension6022900Yes: over 30 days and over 20 at once; also over 500 person-days
Long job, small crew1205600Yes: over 500 person-days

After the answer

If the project is notifiable, the client (or someone acting for them) submits form F10 online through HSE. The notice must be displayed in the site office where workers can read it, and updated if the particulars change. Notification does not decide whether you need a construction phase plan: every project needs one. The construction phase plan builder will draft it. For the traps in the word "simultaneously" and what happens when the programme grows, read our CDM 2015 notifiability guide.

Frequently asked questions

When is a construction project notifiable under CDM 2015?

When the construction work is scheduled to last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project, or to exceed 500 person days (regulation 6).

Who has to notify HSE?

The client, in writing, as soon as is practicable before the construction phase begins. The client may ask someone else to submit it on their behalf. For a domestic client, the contractor (or principal contractor) normally takes on the client's duties, including notification.

How is a project notified?

Using HSE's online form F10. HSE no longer accepts paper, email or posted notifications. The notice must also be displayed in the construction site office where workers can read it.

What is a working day under CDM 2015?

Regulation 2 defines a working day as any day on which construction work takes place, so weekend working counts and days with no work on site do not.

Notifiability that follows the programme Veystrum works out regulation 6 for each project from its programme and site diary, records the date the threshold was crossed, and flags a notifiable project with no F10 recorded.

Talk to us about a pilot

General information, not legal advice The authoritative text is the Construction (Design and Management) Regulations 2015 and HSE's guidance L153. Where a project's figures are close to a threshold, take advice.